Three signs on a wall: every task has a home, every project has a purpose, every program has an owner

Home / Programme & Project Planning

Programme & Project Planning Framework

One structure for all the work in a major event.

The planning structure behind Winter World Masters Games 2028 and the Lahti 2029 FIS Nordic World Ski Championships. It puts every task in one place, with an owner, so your leadership team can see where the work stands.

Winter World Masters Games 202846 programmes · 354 projects
Lahti 2029 FIS Nordic World Ski Championships66 programmes · ~600 projects

01 / The problem

In a major event, it is hard to see who does what.

A major event runs across a city, a rights holder, venues, federations and suppliers. Everyone works hard. But nobody sees all of the work in one place.

What usually happens

  • Work falls between organisations. Everyone thinks someone else is doing it.
  • Two teams do the same work. It is found out late and paid for twice.
  • Meetings become status updates. Little time is left for decisions.
  • Nobody knows who is responsible. Often in the last six months.

02 / How it works

Four levels. Every task in its place.

Each level answers one question. The examples are from Lahti 2029.

1
BasketWhich leader is responsible for this area?E · Festival & Experience
2
ProgrammeWhat part of the strategy or contract does it deliver?E3 · Ceremonies
3
ProjectWhat gets done, by whom, by when and at what cost?E3.1 · Opening Ceremony
4
Sub-projectWhat exactly is needed, how many and at what price?E3.1.2 · Performers

Every project has four things:

TimelineBudgetPeopleReason: the contract, strategy or need behind it
Where the work comes from
Must doContracts and law. Hosting agreement, rules, permits.
Need to doEvent essentials no clause names: power, safety, access, people fed.
Want to doThe strategy the organising committee chose.
Could do / Won't doParked or decided no. Stays visible, with the reason.

If a piece of work has no reason, it does not go in the plan.

03 / In use now

Two championships. Same structure.

Winter World Masters Games 2028

Three host cities, eleven sports, a small core team.

5baskets
46programmes
354projects
2,153sub-projects

Focus areas

  1. Sports12
  2. Participant experience7
  3. Production10
  4. Governance & leadership9
  5. Revenue8

Every project has an owner and is marked must, need or want. The structure was approved as a whole and is used every day in the project tool.

masters2028.com →

Lahti 2029 FIS Nordic World Ski Championships

Strategy: Place To Be. Four objectives, 50 critical success factors.

8baskets
66programmes
~600projects
~4,000sub-projects

Focus areas

  1. A · Management & Governance11
  2. B · Sports & Competitions11
  3. C · Brand & Marketing6
  4. D · Sales, Partnerships & Revenue9
  5. E · Festival & Experience7
  6. F · Broadcasting & Media6
  7. G · Event Operations & Workforce10
  8. H · Legacy, Sustainability & Community6

Each basket has one responsible executive. Each project has its own budget line, so you see what every piece of work costs.

What leadership gets

The whole event on one page.An owner, a deadline and a budget for every project.Meetings for decisions, not status updates.

04 / Ways to use it

Build it yourself, or with me.

05 / The system

Run the structure in Major Event OS.

Major Event OS is the event director's operating system for major events. It holds every contract, project, budget line and risk in one structure, followed every week, with a one-page monthly report for the board.

  • The same levels as this framework. Baskets, programmes and projects, each with an owner, a source and a budget role.
  • Money tied to the plan. Every budget line belongs to a project. A signed contract enters the forecast the same day.
  • Status from the work. Calculated from dates, decisions and commitments, never typed.
Major Event OS: the programs board of an example event, with owners and readiness checks

Programs board, example event. Pricing starts at €497 a month.

Questions

Frequently asked

How does the Blueprint structure an event’s work?

It breaks the event into four connected levels. Programmes are the streams that deliver the strategy, owned at leadership level. Projects are concrete work with a purpose, an owner and a deadline. Task groups are work packages grouped so nothing hides. Tasks are what gets done this week, by whom. Every task has a home.

Can project management software do this instead?

Software is excellent at tracking work. It does not tell you what should become a programme, what belongs inside a project, or who owns each level. Those are structural decisions and they come first. Once the structure is right, Notion, Excel, a PMO system or the Bonacube App all become easier to use. The structure travels; the software is replaceable.

Where should a newly formed organising committee start?

With the one-day workshop. That is where most organising committees should begin. In one working day we identify the main programmes, define the major projects, review ownership, find the missing areas and build the planning logic. Not the finished event plan, but a structure the organisation can build on for the next several years.

Start where your organisation is today

Give the work a structure before the work grows.

The earlier the structure exists, the less rework the organisation carries for the rest of the project.